Power System Operation and Control Mid - II, November - 2014
1.The unit for speed regulation of governer is
-
HZ
-
HZ/MVA
-
HZ/MW
-
none of the above
-
Answer: C
2.The speed regulation D for a large size alternator is about
-
10 HZ/MW
-
5 HZ/Mw
-
1 HZ/MW
-
0.02 HZ/MW
-
Answer: D
3.The rate of drop in frequency of control inlet valve due to an increase in generation of power (dPG) on prime mover is called
-
speed regulation
-
speed efficiency
-
governer operation
-
none of the above
-
Answer: A
4.What is the condition for uncontrolled case in a two area system
-
ΔPc1=0
-
ΔPc2=0
-
ΔPc1=ΔPc2=0
-
none of the above
-
Answer: C
5.Two alternators are running in parallel. If the field of one of the alternator is adjusted it will
-
reduces its speed
-
change its load
-
change its p.f.
-
change its frequency
-
Answer: C
6.The synchronizing coefficient between two areas of a two area power system is
-
A
-
B
-
C
-
D
-
Answer: C
7.Frequency of the resonant vibrations lies in the range of
-
50-100 Hz
-
10-20 Hz
-
100-200 Hz
-
none of the above
-
Answer: A
8.Steady state frequency error in a single control area can be eliminated by
-
proportional control
-
integral control
-
derivative control
-
proportional + derivative control
-
Answer: C
9.Shunt capacitance is usually neglected in the analysis of
-
short transmission lines
-
medium transmission lines
-
long transmission lines
-
medium as well as long lines
-
Answer: A
10.For the same voltage boost, reactive power capacity is more for a
-
shunt capacitor
-
series capacitor
-
same for both
-
none of the above
-
Answer: A
11.For a good voltage profile under no-load condition, a long line needs _________________ at receiving end.
Answer: Shunt Reactor
12.For a small KVAR requirements ____________________ is more economical.
Answer: Static Or Shunt Capacitor
13.The series compensation increase ______________________.
Answer: Stability Limit
14.For a lumped inductive load with increase in supply frequency, P ________________ and Q ____________________.
Answer: Decreases, Increases
15.The unit of frequency bias parameter is _______________________.
Answer: No units
16.If the two areas are identical, the relation between two line powers is ________________
Answer: P tie,1 = -P tie,2
17.If we are interconnecting two areas, the steady state frequency error is ______________ by 50%.
Answer: Reduced
18.Load frequency control is achieved by properly matching the individual machines _____________.
Answer: Turbine Inputs
19.Load frequency control uses ______________________control.
Answer: Both Proportional And Derivative Control
20.For stability and economical reasons, we operate the transmission lines with power angle in the range ______________________.
Answer: 300 TO 450